Kitchen Renovation Timeline in Melbourne: From Planning to Handover
A kitchen renovation timeline in Melbourne starts well before the old cupboards come out. Layout decisions, appliance specifications and delivery dates all shape when work can begin and when you can cook at home again.
This guide follows the job from the first sketch to handover. Use it to ask better questions about your program, plan a temporary kitchen and understand why one unfinished item can hold up the next trade.
Key takeaways
- Ask for two timeframes: the full project program and the period your kitchen will be unavailable.
- Confirm the layout, appliances, finishes and delivery dates before committing to demolition.
- Allow for the sequence between cabinetry, benchtop measurement, fabrication and final connections.
- Keep a written record of changes and their effect on cost and completion.
How long does a kitchen renovation take?
There is no reliable finish date until the scope, site conditions and supplier commitments are known. Replacing cabinets within the existing room has different requirements from moving plumbing, removing a wall or extending the house.
Ask your builder for a dated program that includes design, any approvals, ordering, site work and handover. A quote that only describes the installation period may leave out the time needed to manufacture cabinetry or arrange a benchtop check measure.
Two dates to clarify: When will the existing kitchen stop being usable, and when will the sink and cooking appliances be safely connected and ready to use? Those milestones matter when planning meals, accommodation and family routines.
Kitchen renovation timeline at a glance
| Stage | What happens | Ready to move on when… |
|---|---|---|
| 1. Brief and layout | Measure the room and agree how it needs to work. | The layout and appliance positions are settled. |
| 2. Scope and approvals | Resolve drawings, permit requirements, inclusions and responsibilities. | Required approvals and the agreed building scope are in place. |
| 3. Orders and bookings | Confirm products, manufacture and delivery arrangements. | Critical items and trade dates have been checked. |
| 4. Strip-out and preparation | Disconnect services, remove the old kitchen and prepare the room. | The site is ready for the specified cabinetry and finishes. |
| 5. Cabinets and benchtops | Install joinery, complete any final benchtop measure, then fabricate and fit. | The work surfaces and required openings are ready for final connections. |
| 6. Fit-off and handover | Complete fittings, test services, inspect and record outstanding items. | The agreed completion requirements have been met. |
This is a sequence guide, not a fixed-duration schedule. Flooring, painting and splashbacks need to be placed in the program according to the selected products and installation requirements. Some work can overlap; other tasks must wait.
Before demolition: make the decisions that affect the build
Start with the way you use the room
Write down what is awkward in your current kitchen. It might be a dishwasher that blocks a walkway, too little preparation space beside the cooktop or storage that is difficult to reach. Keep those problems in the brief when comparing layouts.
Bring a measured plan, photos and a list of appliances you intend to keep. Check door swings, appliance access, bin storage and the route through the room. Our Melbourne kitchen renovation service is a starting point for discussing the building scope.
Check approvals before setting the start date
Do not assume an internal renovation is automatically exempt from permits. Ask a registered building surveyor about building permit requirements and the local council about planning requirements for the proposed work. Removing walls or changing the building can need further design and engineering input.
Consumer Affairs Victoria explains plans and permits, including the importance of documenting the work before signing. Identify who is responsible for each approval in your agreement.
Finalise the appliance and finish schedule
Choose the actual model numbers for the oven, cooktop, rangehood, dishwasher and fridge before the cabinetry details are finalised. Their dimensions, ventilation and service requirements can affect the joinery and electrical work.
- Confirm cabinet finishes, handles, benchtop material and edge details.
- Check the sink and tap specifications, including any required cut-outs.
- Agree splashback, lighting and power point locations.
- Ask suppliers to confirm availability and delivery arrangements in writing.
- Record who supplies each item and who checks it on arrival.
Prepare for the time without a kitchen
Before strip-out, agree a temporary food preparation area outside the work zone. Plan access to drinking water, refrigeration and washing-up facilities. Ask the electrician about safe appliance use in the temporary location.
Discuss dust separation, protection of floors, delivery access, waste removal and where trades will work. Children and pets need a safe route that stays clear of the site. If your kitchen is part of a larger home renovation or extension, ask how the wider work affects access to other rooms.
Older homes: Have suspect materials assessed before disturbing them. Asbestos can affect the scope and sequence of removal work. The Australian asbestos safety guidance for home renovators is a useful starting point for planning this check.
During installation: understand what must happen first
Service work and room preparation
The relevant trades disconnect services before removal and prepare the new service locations to suit the agreed drawings. Once cupboards and finishes are removed, concealed conditions can become clearer. Damaged flooring, uneven walls or unexpected services may need to be addressed before new joinery goes in.
If something changes, ask for the proposed solution and its impact on the program before the affected work proceeds. Keep the drawings and selections current so each trade works from the same information.
Cabinetry, then the benchtop check measure
For a custom benchtop, the final measure may depend on the cabinetry being installed and ready. Fabrication and fitting then become separate milestones. Ask your supplier when the measure can occur, which fixtures must be available and what lead time applies after approval.
For example, the IKEA Australia custom benchtop readiness guide (PDF) requires installed cabinetry before check measure. It also notes that some splashbacks may need measurement after the benchtop is fitted. These are supplier-specific requirements, so confirm the sequence for your selected products.
Splashbacks and final connections
The splashback, tap, sink, appliances and electrical fittings need to be coordinated with the finished surfaces. Allow the specified curing or drying time for the products used. Ask when the room can safely be cleaned and used, rather than assuming it is ready as soon as it looks finished.
Electrical installation work must be carried out by appropriately licensed workers. Keep the Certificate of Electrical Safety with your handover documents, along with applicable plumbing documentation and product information.
How to keep your kitchen renovation timeline on track
A useful program identifies decisions as well as trade visits. If a selection is due on Friday, knowing that date early gives you time to compare options without holding up manufacture.
Five checks before the old kitchen comes out
- Is the latest layout approved, including appliance and service positions?
- Are required approvals in place and the construction scope agreed?
- Are critical products available, with delivery dates confirmed?
- Are cabinetry, benchtop measurement and trade bookings coordinated?
- Do you know who will provide updates and authorise any changes?
Keep a small decision register with the item, the person responsible and the agreed deadline. If you change a finish or appliance, ask whether it affects drawings, existing orders or another trade. A replacement product that is in stock may still require a different cabinet opening.
For work approaching holiday periods, confirm supplier closures and trade availability before relying on a handover date. Build your household plans around the written project program and keep some flexibility for issues that cannot be confirmed until the room is opened up.
Handover: check the details while the team is there
Walk through the kitchen with the builder and compare the completed work with the agreed scope. Check drawers and doors, appliance clearances, visible finishes and the operation of installed fittings. Ask for a demonstration of unfamiliar controls.
- Record any outstanding items and the agreed next steps in writing.
- Collect appliance manuals, warranties and care instructions.
- Keep relevant compliance certificates and any required inspection documents.
- Confirm which cleaning products are suitable for the benchtop, cabinetry and splashback.
Agree how to report an issue after handover. A clear record is more useful than trying to remember a conversation once the room is back in everyday use.
Kitchen renovation timeline questions
Can I stay at home during a kitchen renovation?
Possibly, depending on the extent of work and safe access to the rest of the house. Discuss service interruptions, dust, noise and temporary food preparation arrangements before deciding. Structural work or a wider renovation may change what is practical.
Should I order appliances before demolition?
Confirm the specified models and availability before demolition, and agree the delivery dates with the builder. The team may need certain items on site for measurement or installation. Avoid ordering from an early sketch before dimensions and responsibilities are checked.
Will keeping the existing layout make the project quicker?
It can reduce the extent of changes, but it does not remove the need to inspect services, confirm product availability or coordinate trades. Ask for a program based on the actual work, even when the sink and cooktop stay in the same positions.
What should I bring to an initial discussion?
Bring photos, an existing plan if available, your priorities, preferred appliances and an indicative budget. Mention any date you hope to finish by and why it matters. ODA Homes can discuss the proposed building work and the information needed to assess the next steps.
Planning your kitchen renovation?
Tell ODA Homes what you want to change and what matters most in your new kitchen. We can discuss the building scope and the next steps for your Melbourne home.